Coal Mining Quagmire in India - My article in the Mining India magazine
Coal mining in deep rut is pulling power sector down
Coal mining has been the fulcrum for power sector in India. One
of the most conspicuous trends in energy sector has been the capacity addition
in power generation, in which for the first time the expected addition from
private sector alone would cross 10,000 MW in FY 2012. This also when
simultaneously the average plant load factor for coal based power plants has
taken a dip to about 64% and is also expected to fall further. The major reason
for lower than expected capacity utilization has been fuel issues. Coal
production from domestic sources saw stagnation while generation saw capacity
addition; imports grew but prices and foreign exchange dynamics kept
affordability distant. Sector also saw little on reforms and distribution
companies’ financial losses and apprehensions about their viability kept
finances for them as well as for generation projects getting tough to
secure.
The three biggest challenges for power sector in India are –
fuel availability & pricing; cost of supply and tariff gap; and open access
implementation. These put together have also led to issues in financial
closure. Coal from domestic sources look getting scarce as CIL is unable to
produce at the expected growth rate while the political controversies will
cause few coal blocks to be invested in and developed. These notwithstanding,
new coal mining projects have had severe challenges of land acquisition,
rehabilitation & resettlement, environmental and forest clearances and such
others. Imports have been rising and prices of coal although on a downslide for
now do not make imports an affordable option. The story on the fuel side looks
gloomy. On the cost of supply and tariff gap, efforts need to be made in the
right earnest to have cost reflective tariffs. Several aggressively bid case 1
bids have now been referred to courts on fuel cost issues. It is obvious that
unsustainable tariffs would not see several projects take off. Interestingly,
there are however pockets of demand that can afford to pay higher tariffs but
are not connected with supply sources due to financially broke distribution
companies and their claims to open access charges. These have muffled the
growth opportunities for the power sector.
The one most critical part of the value chain that
determines affordability of power, which conforms to the adage that mitigation
against default risks is low tariff, is availability of low cost domestic coal.
The government can open up the coal mining sector for independent mining
companies, including foreign majors, with expertize, experience and technology
to help India exploit its large untapped resources. Greater the supplies from
domestic sources and lower the dependence on one monopolistic producer, the
prices of coal would be determined by economic equilibrium and can remain
lower. However, till such time that market stabilizes, regulatory supervision
of such mining ventures and price fixation of coal produced can be done. That
can certainly be the biggest boost the power sector can get from the
government.
Not that this has not been comprehended fully, and as a
result the Coal Mines Nationalization (Amendment) Bill 2000 was presented in
the Indian parliament. However, pending it still is in the upper house for the
lack of political accountability and willingness to move towards reforms.
Coal block allocation has been in the news
Much has been investigated and written about the levels of
scam in coal mining sector, including the astronomical numbers of notional
losses to the government for not following the auction route for coal block
allocation. Resource ownership is a key competitive advantage for businesses
now since raw materials occupy significant proportion of costs in the energy
and metals manufacturing value chain. Given this, the rush to capture resource
assets is an obvious conclusion. The trend, however, is more prominent in India
and China while globally, there are firms still focused largely on their core
competencies. Looking at the regulatory and statutory frameworks in India and
economics of energy generation and manufacturing, the trend in India is unlikely
to change in future as well. The much sought after coal resources were
allocated through a screening committee mechanism that evaluated applications
on parameters like - status (stage) level of progress and state of preparedness
of the projects; net worth of the applicant company (or in the case of a new
SP/JV, the net worth of their principals); production capacity as proposed in
the application; maximum recoverable reserve as proposed in the application; date
of commissioning of captive mine as proposed in the application; date of
completion of detailed exploration (in respect of unexplored blocks only) as
proposed in the application; technical experience (in terms of existing
capacities in coal/lignite mining and specified end use); recommendation of the
administrative ministry concerned; recommendation of the State Government
concerned (i.e. where the captive block is located); and track record and
financial strength of the company. This method of evaluation can be as good as
the implementation. And when the number of application reached 750 for 16 blocks
for power generation in 2006 round, the method was stretched beyond its normal
application. Hence, the questions are raised and lack of objectivity and
transparency has led to allegations of corruption.
Notwithstanding the legal repercussions, It is critical for
the captive blocks to be developed efficiently so that resources are made
available for power generation. Regulatory reviews of cost of mining can be a
way to ensure consumers are protected and the developer is adequately
compensated. The current proposal by the Ministries of Power and Coal to allow
continuation of captive coal block allocation only when the attached power
project sells power through competitive bidding may have its own limitation. Forcing
the developers to bid for tariff based competitive bids may not always achieve
these objectives of consumer protection as well as incentivization of project
development as the competition is typically market determined and discovered
tariffs may still have super profits or unviability, both unwarranted. However,
liberalizing the sector such that there is regulated competition in coal mining
would do good to the sector.
Coal linkages have been challenged too
Coal sector in India suffers structural deficiencies due to
statutory restrictions, resulting in rationing for coal produced as well as for
coal resources. These deficiencies have aggravated in the times of severe
shortage. Large number of applications received for relatively smaller number
of coal blocks and Standing Linkage Committee issuing letters of assurance for
quantities that far exceed the coal likely to be produced by CIL are
manifestations of this. In such circumstances, process quality and efficiency
of its implementation open themselves for scrutiny, and quite rightly so.
Processes based on merit are as good as the implementation.
With growing number of applicants for linkages, the process has been evolving
too to take care of emerging challenges, However, in any merit evaluation,
subjectivity cannot be eliminated altogether, which is where the issues of
equity and transparency arise. Linkages have two-fold story - one of getting
the letters of assurance (LOA) from the standing linkage committee (SLC) that
equals an in-principle approval, followed by the other of getting the LOA converted
to Fuel Supply Agreement (FSA) with the CIL subsidiaries. Both follow a set of
instructions that prescribe for the degree of progress on the end use plant
with certain identifiable milestones. While for issue of LOA, the evaluation on
the parameters rate the applications on points, which have evolved in the last
couple of years, meeting all the milestones on schedule is essential for LOA to
convert to FSA.
Evaluation of applications for LOA depends upon scrutiny
similar to that for coal block allocation, where agencies at the centre and at
the states are involved and their recommendations are considered for the
purpose.
Mine Developer cum Operator (MDO) selection are next in the queue
Equally important observations are with respect to mine
development through contract mining. Turnkey project commissioning through Mine
developer cum operator (MDO) route can be an effective way for participation of
private and foreign contract miners. Standardizing documents for MDO selection
may serve the purpose of enhancing efficiency and transparency, as has been the
result in tariff based competitive bidding in power sector. However, questions
would remain pertaining to scope of work for MDO wherein there could be
variations in land acquisition, rehabilitation & resettlement, clearances
& approvals, capital expenses for immovable assets, and such others.
State government and some private captive coal block owners
have preferred the MDO route for fine development and there are various
business models, from outsourcing to joint ventures, in view of suitability
from investment objectives and risk sharing principles. Coal mining being a
unique proposition at each location the practice has been to devise appropriate
contractual relationships. However, in matured mining industries of Australia
and elsewhere, the contract miners' roles and responsibilities have evolved and
hence, standardized contracts are being used.
In India, due to captive coal block allocation, the end
users such as the power generation companies or steel manufacturers have been
awarded coal blocks and many do not have any experience in coal mine
development. State owned power utilities have lacked financial resources as
well for the development, where problem has been compounded for them when the
coal blocks they have been given are outside of their own states.
MDO selections in several such cases have also not been
transparent. These are the challenges faced in a competitive scenario but where
the competition is lop-sided, the market participants in the contract mining
tenders themselves have not much experience or expertize and hence, the
processes of selection have tended to be liberal on technical qualification
criteria. Often, the financial criteria have been formulated with no specific
needs or objectives in mind. As a result, the awards have been questioned and
are likely to be questioned in times to come.
Conclusion
The more labyrinthine the legislations, regulations and
rules become, the greater are the chances of hoarding, profiteering,
corruption, unlawful activities and such other manifestations of rut.
Simplicity and ease of compliance reflects in the functions of an industry.
From the legislative and regulatory points of views, it will be better for
India to adopt openness in coal mining business and let there be competition in
production and supplies. There needs to be a wide range of market participation
– from independent miners to contractors, from producers to traders, from
logistics service providers to financiers, from risk managers to speculators –
all with regulatory supervision so the excesses of open markets are not allowed
to distort the market the other way. Vested interests cannot be checked by
creating layers after layers of regulations, under multiple agencies at central
and state levels. Repeal of the
outlived-its-shelf-life Coal mines Nationalization Act can be a good
beginning.
3 Comments:
That's quite insightful!! I am looking forward to following your blogs sir!!
-Manjunath Chenna
ISM 2010
Very insightful article sir. Opening up coal markets for foreign players will certainly help in price being determined by market.
I would like to know your views on the kind of contract these foreign players should be offered. Should they be provided a concessionary agreement with the right to sell coal, or a Profit Sharing kind of Contract?
"Forcing the developers to bid for tariff based competitive ,,,,,still have super profits or unviability, both unwarranted"
Could you enlighten us more on this part.
Also, in the current scenario where private companies have benefited from tax payers money due to corruption, don't you feel that common man will be a bit skeptical with privatization.
Like we have clearly seen how big players like NTPC could not get any coal blocks while very small companies have been alloted blocks.
---
Kumar Gaurav
Thank you, Manjunath and Gaurav, for encouragement. Some of the things that you've asked, Gaurav, are explained below:
1) When you force companies to bid, they will see the market and bid. If there is limited market participation, the player will bid higher number and make super profit. On the other hand when someone is desperate and wants to win a bid just to retain a coal block, it will bid low and the project will turn unviable. Both these are not desirable. Therefore, it is required that competiton be fair, open and well represented by market participants.
2) Idea of privatization is now because the production is required now when the PSUs are failing. As far as corruption is concerned, it has been due to sidesteps, because of subjectivity in the process. A robust and well planned privatization can be frre of corruption (as has been the case of 3G spectrum allocation).
Post a Comment
Subscribe to Post Comments [Atom]
<< Home